Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Imoprting MS project 2010 into Primavera Risk Analysis

No replies
William Millar
User offline. Last seen 11 years 34 weeks ago. Offline
Joined: 31 Mar 2012
Posts: 4
Groups: None

Hi all,

 

I have discovered an issue while importing MSP files into PRA.

This arises when the MSP file contains tasks which are already underway i.e started before the import date.

PRA does not carry through this date from project but uses a later date (I think the one the MSP file was created on - also after the tasks which are underway).

 

THe resulr of all this is theat the finish date are very different between the MSP and PRA files.

 

THis might be a silly question but how do I make sure that PRA imports the dates exactly as they are in MSP?

 

Many thanks

 

W