Hi,
after several days self-training on Primavera Risk Analysis, I still can't simulate the following sequence:
-during an iteration, the activity duration is above its deterministic duration, pushing the succeeding milestone in delay.
- in that case, I would like to impact on PRA the schedule and costs in accordance with these 2 scenarios (previously chosen before starting the simulation, I mean only 1 scenario will apply during all iterations):
> SCENARIO 1 (RECOVERY PLAN, MILESTONE NOT IN DELAY) : more resources put in a certain duration prior to the milestone finish date, and “limit” the activity duration iteration in order to not put the milestone in delay. In this case, no liquidated damage needs to be added. => impact cost, but no real impact schedule.
> SCENARIO 2 (LIQUIDATED DAMMAGES, MILESTONE IN DELAY): liquidated damage due to milestone delay would impact Project costs. => impact cost, and impact schedule (as the milestone finish is after the baseline in that case)
The goal of this being to properly simulate recovery plan, liquidated damages impact and/or extension of time (with potential associated cost, in case of contractor supporting the cost, like in LTSK project as an example)
Maybe these can be very easily done with basic features (baseline automatical comparison setting off cost impact, what-if scenario possibilities,etc.) but if anyone can help me for this, or any indication regarding PRA possibilities, would be really great!!
Regards
Replies