Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Inspection as a risk

1 reply [Last post]
Dominador Santos
User offline. Last seen 11 years 29 weeks ago. Offline
Joined: 17 Jul 2010
Posts: 5

Hi All,

Do you agree that Inspection can cause delay on the completion of activities considering the time of submission and resubmission of RFI's. Also, the time of waiting for the inspectors instead of doing the work continuously.

May I know your opinion.

Thanks and regards,

Dominador Santos

Replies

Mike Testro
User offline. Last seen 4 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Dominador

Time for test/Inspections should be built into your programme as individual tasks.

Then if they take to long or are delayed you can demonstrate the delay.

Best regards

Mike Testro