Inspection as a risk

1 reply [Last post]
Dominador Santos
User offline. Last seen 8 years 22 weeks ago. Offline
Joined: 17 Jul 2010
Posts: 5

Hi All,

Do you agree that Inspection can cause delay on the completion of activities considering the time of submission and resubmission of RFI's. Also, the time of waiting for the inspectors instead of doing the work continuously.

May I know your opinion.

Thanks and regards,

Dominador Santos

Replies

Mike Testro
User offline. Last seen 14 weeks 4 days ago. Offline
Joined: 14 Dec 2005
Posts: 4407

Hi Dominador

Time for test/Inspections should be built into your programme as individual tasks.

Then if they take to long or are delayed you can demonstrate the delay.

Best regards

Mike Testro