Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

P3e

Senior Planning Engineer, Mouchel Parkman, Jubilee Line Signals Upgrade

START Date: 
February, 2006
END Date: 
February, 2008

Key Responsibility Areas:

 

  • Develop the 16-week Rolling Programme at Level 4

 

  • Develop the 5-week Rolling Programme (Work Plan Level 5)

 

  • Provide inputs to the weekly progress report and 4-weekly Period Progress Review Report, including current performance indicators and analysis derived from quantified progress / actual labour hours / actual costs inputted on to the PMP, identifying any significant schedule and costs variances to be explained / further investigated.  Also report on the stat

Assistant Project Manager / Project Planner, Network Rail Thameslink, Thameslink Programme

START Date: 
October, 2009

As a Project Planer working with in central function team my main responsibilities are to provide programme planning support to Thameslink Central Engineering and Sponsor teams. Working on my own initiative and liaising with project’s teams to develop the best logic for the live programmes, collecting project data and transferring it in to programme plan. Updating activity schedule and creating project’s baseline. Generating Programme progress, Stage Gate, Coded reports and supporting engineering teams on accountability review meetings.

Planning Lead Engineer, Nargan Engineer & Constructor Company, South Pars Gas Field Development Phases 15 &16 & 22& 23 & 24 & 13

START Date: 
September, 2002

Planning Lead Engineer of South Pars Gas field Development Phases 15 & 16 & 22 & 23 & 24 and 13 - EP Contract - Nargan Engineer & Construction Company

Commissioning Planner, Network Rail, FTN / GSM-R Programme

START Date: 
January, 2006
END Date: 
May, 2008

 

Network Rail FTN / GSM-R Programme (Planner to the Commissioning team (6 month rolling Contractor Position)                                                                                  

The FTN /GSM-R Programme:

Project Planner, Network Rail, National Level Crossings

START Date: 
March, 2008

 

In this role I’ve experienced the application of project planning, managing a portfolio to an approximate annual value of £150 million. I’ve developed Project Plans from Development, through into realisation, to handover and project close out, including monthly performance reporting to the Project team. I’ve acted in a supervisor role within the Project Planning team. Toolset used primarily has been Primavera P3e version 5, Microsoft Project 2007 and MS Excel for financial data analysis. 

Claims and Contracts Managment/ Project Managment and Control, Thost LLC, EPC Water/ Material Production/ Power Generation/ Renewables

START Date: 
January, 2010
END Date: 
October, 2011

EPC Water Plant Project, Abu Dhabi: Seconded as Claims and Contract manager to a well-known power and automation company on an EPC water plant project. As part of the EPC Contractors Project management team responsible for the contractual correspondence, including claims and claim evaluation (cost and time) towards the Employer and Subcontractors (e.g. main contractors, design consultant and Suppliers). In addition, participation in negotiations.

Market Place

Primavera P6 and Microsoft Project books, on-line video training courses and training material available from an internationally recognised publisher. Teach yourself using on-line or book based learning or run your own in-house or public courses.
Syndicate content