Primavera P6 - Activities In-Progress and Activities going to start

1 reply [Last post]
pradyumna yarrams...
User offline. Last seen 11 years 4 weeks ago. Offline
Joined: 27 Mar 2013
Posts: 2
Groups: None

Hi,

How do I get the activities in-progress and activities which are going to start in next 2 weeks using Primavera? Thanks for your help.

Thanks,

Pradyumna

Replies

Arun Kumar
User offline. Last seen 3 years 50 weeks ago. Offline
Joined: 26 Mar 2012
Posts: 7

Hi,

Right Click on Window. Click on Filters - Click on New. 

Enter Fliter name as 2 Weeks Look ahead

After that enter the parameters shown below

 

where  -  start  -                is within range of           - DD                     - DD+2W

Or       -  Activity status      - equals                        - In progress

Mark Click on 2 weeks look head.

Then you will get activity in progress for next 2 weeks.

Hope you will get the solution. 

 

Arun Kumar