Andrew Owenson
User offline. Last seen 1 year 1 week ago. Offline
Joined: 18 Jun 2008
Posts: 68
Groups: None

Could someone tell me if there is a simple way of assigning a wbc to multiple tasks - I have to issue a contract programme by the end of the day and I have imported a programme without ant WBS codes in it!!

 

Andrew

Replies

waseeq khan
User offline. Last seen 12 years 32 weeks ago. Offline
Joined: 20 Jul 2011
Posts: 2
Groups: None

Hi Alexandre,

 

Thanks it works. You mad my task simpler.

 

 

Regards

Waseeq

Rockzy Sales
User offline. Last seen 13 years 14 weeks ago. Offline
Joined: 19 Dec 2010
Posts: 19
Groups: None

Hello,

 

Will filter and fill down work? ;-)

 

cheers,

the Rock

Mohammad Aslam
User offline. Last seen 11 years 33 weeks ago. Offline
Joined: 29 May 2007
Posts: 11
Groups: None

Hi Andrew,

Do the following steps

Go to File - Export 

Select spreadsheet

Select Activity

Select Template (modify Template)

Select Columns to be exported to excel spreadsheet (Activity ID, Name & WBS code)

Change WBS code in WBS columns or copy paste (in Excel spreadsheet) the WBS code of activities in the same WBS element. 

Make the changes, save the spreadshhet.

Import the same excel file into the project.

it's done

 

Hope this help.

 

Mohammed Aslam