Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Why does Progress % does not apper while summarizing

1 reply [Last post]
Haresh Jayanth
User offline. Last seen 1 year 30 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219
Why does, while we are summarizing the project with wbs level , any progress % (for eg activity % complete column), does not show any % at WBS level , even when we add resource & cost for all activities.

The summarized % column is blank....

Can anyone explain......

Replies

Rodel Marasigan
User offline. Last seen 15 weeks 5 days ago. Offline
Joined: 25 Oct 2006
Posts: 1516
Haresh,
There are only two fields that would not summarize total in summary band, Physical % complete and Activity % Complete which is represented by Performance % Complete.
There are 3 types of % complete type, Duration, Unit and Physical. Duration is base on duration (Yr, Mth, Wk, Day or Hr), Units is labor, non-labor and material and Physical = Physical.
All three of them are represented by Activity % complete and Performance % complete (which ever is set on % complete type) therefore if total is required in summary band Performance % Complete should be used and if not then Activity % Complete is the appropriate to use.

To show the total in Summary Band, under Group & Sort -> Display Option tick Show Group Total.