Why does, while we are summarizing the project with wbs level , any progress % (for eg activity % complete column), does not show any % at WBS level , even when we add resource & cost for all activities.
The summarized % column is blank....
Can anyone explain......
The summarized % column is blank....
Can anyone explain......