Hi Planners,

                 Kindly inform me if there is any options in P6 to show average date while summarizing the schedule & how can we hide the dates in the summarization sheet. Kindly help me ASAP.

 

Thank you

Krishna

Replies

Hi Daniel,

             Thanks for your suggestion. And i've to clarify more that while summarize by groups upto level 4, i need to see dates on 2,3,4th level, but in my 1st level i've hide it. is it possible? i hope that you understand my question. Kindly give me your advice ASAP

Thank you,

Regards,

Krishna

Hi Daniel,

             Thanks for your suggestion. And i've to clarify more that while summarize by groups upto level 4, i need to see dates on 2,3,4th level, but in my 1st level i've hide it. is it possible? i hope that you understand my question. Kindly give me your advice ASAP

Thank you,

Regards,

Krishna

Daniel Limson
User offline. Last seen 2 days 22 hours ago. Offline
Joined: 13 Oct 2001
Posts: 318

 

Krishna,

In summary, P6 will use the earliest start date and the latest finish date to calculate the total duration of the summary bar and it uses calendar days at 7 days per week.

If you do not want to see the Start and Finish Dates , you can always remove the column.

 

Best regards,

Daniel