Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Why does P6 does not show BL2 % Complete

1 reply [Last post]
Haresh Jayanth
User offline. Last seen 1 year 29 weeks ago. Offline
Joined: 24 Aug 2006
Posts: 219

Dear All,

I have assigned two programs as primary baseline and secondary baseline. But i am not able to get the column showing % complete for the secondary baseline program i.e. BL2.

How to solve this problem.

 

Pls do reply.

 

regards,

 

Haresh Jayanth

Replies

michael ramos
User offline. Last seen 2 years 28 weeks ago. Offline
Joined: 10 Feb 2009
Posts: 25
Groups: None

you can try a workaround

assign your BL2 as project baseline and copy the schedule % to UDF using global change (after shifting the data date)

then assign BL1 as project baseline and put your BL2 as primary

now you can compare sched % (BL1) and UDF (BL2)