Why when changing a resource does it change the 'Budgeted at completion' to equal the duration?

2 replies [Last post]
DAVID SMITH
User offline. Last seen 10 years 37 weeks ago. Offline
Joined: 24 Mar 2004
Posts: 28

When I manually change a resource, it changes the budgeted units to equal the duration on the activity.

what setting is doing this, i presume it is a tick box somewhere.

Can anyone please help?

Many thanks

Dave

Replies

Alfredo Jr. Hubilla
User offline. Last seen 4 years 40 weeks ago. Offline
Joined: 6 Feb 2012
Posts: 20

Try go to the Projects Details, Resources tab, and tick the Resources can edit activity assignment percent complete..

 

Hope this can help.

Raymund de Laza
User offline. Last seen 32 weeks 4 hours ago. Offline
Joined: 23 Nov 2009
Posts: 762

Dave,

Make the Max Units/Time of the resource the same as the previous. 

Hope this will help.