Change Duration when adding extra Resource

4 replies [Last post]
Rodney Jones
User offline. Last seen 3 weeks 1 day ago. Offline
Joined: 18 Jun 2012
Posts: 62
Groups: None

Hi All,

What settings must I use to get P6 to change Activity Duration when I add extra Resources?

Lets say I have I have a 10 day activity with 1 Resource on it and 100 units, when I add an additional same Resource I want the duration to reduce to 5 days and retaining 100 units.

Thanks,

Rod

Replies

Rodney Jones
User offline. Last seen 3 weeks 1 day ago. Offline
Joined: 18 Jun 2012
Posts: 62
Groups: None

How do I close this post?

 

Admin,, please mark this post as Solved.

Rodney Jones
User offline. Last seen 3 weeks 1 day ago. Offline
Joined: 18 Jun 2012
Posts: 62
Groups: None

YES! the User Preferences, Calculation, Resource Assignments option to: Recalculate ... instead of Preserve ...

 

that was the setting I couldn't remember, thanks Alexandre.

Zoltan Palffy
User offline. Last seen 3 weeks 3 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

you can change the duration TYPE to fixed units. As you change the units this will change the duration. 

you can also change the activity type to resource dependent. This will use the resource calendar as opposed to the activity calendar. You usually use this if you have multiple resouces on the same activity.