Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

why does budget hrs change when increasing remaining

3 replies [Last post]
Donovan Govender
User offline. Last seen 10 years 1 week ago. Offline
Joined: 1 Dec 2005
Posts: 20
Groups: None
why does budget hrs change when increasing remaining
and activity has not started

Replies

Rodel Marasigan
User offline. Last seen 5 hours 55 min ago. Offline
Joined: 25 Oct 2006
Posts: 1699
Donovan,

Mark is correct. Check the settings under Project Screen-> Calculation Tab and un-tick the "Link Budget and At Completion for not started activities". This should answer your query.

HTH,
Rodel
Mark Roberts
User offline. Last seen 15 years 51 weeks ago. Offline
Joined: 28 Jun 2007
Posts: 16
Groups: None
Donovan

On the projects screen go to the calculations tab, & check the "Link Budget & At Completion for not started activities." I imagine this is ticked...

Cheers
Mark
David Kelly
User offline. Last seen 1 year 37 weeks ago. Offline
Joined: 19 Oct 2004
Posts: 630
Because your "duration type" has units per time unit fixed.