Cristina Boston
User offline. Last seen 13 years 3 days ago. Offline
Joined: 22 Jul 2009
Posts: 19
I created a copy of a (cost loaded) project in P6. I wonder why in Projects the Total Activities & BAC columns for the copy show 0 (zero).

When I open the copy, it’s fine; has all the data & info I need. But...guess what...the original project gets...depleted from this info (showing 0 activites & costs).

Can anybody explain me what is happeening or why?

Replies

Dieter Wambach
User offline. Last seen 7 years 2 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Gern geschehen! (You’re welcome)

Dieter
Cristina Boston
User offline. Last seen 13 years 3 days ago. Offline
Joined: 22 Jul 2009
Posts: 19
Danke schon Dieter!:~)

Cristina

Dieter Wambach
User offline. Last seen 7 years 2 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Cristina

This is the right approach - we created an EPS-branch "Archive" with special access rights. Change the project status to "What-if".
In addition check the entry under Edit --> User Preferences --> Resource Analysis. It’s self explaining and should be according to your needs.

Regards
Dieter
Cristina Boston
User offline. Last seen 13 years 3 days ago. Offline
Joined: 22 Jul 2009
Posts: 19
OK, I think I found a way. I created a new branch in the EPS structure for Project Copies, and will locate all my copies in there.

Cristina
Cristina Boston
User offline. Last seen 13 years 3 days ago. Offline
Joined: 22 Jul 2009
Posts: 19
Now the problem is...hmmm...the system adds up the data(activites & budget) from my original project + copies. Now I understand why the copies were showing a zero before summarizing.

Where should I locate the copies in order not to affect the EPS info?

Thankfully,

Cristina (obviously I am a beginner in P6)
Cristina Boston
User offline. Last seen 13 years 3 days ago. Offline
Joined: 22 Jul 2009
Posts: 19
It worked. Thank you guys. Now the data shows on all projects (original + copies).

Cristina
Dieter Wambach
User offline. Last seen 7 years 2 weeks ago. Offline
Joined: 15 Jan 2007
Posts: 1350
Cristina

Tools --> Summarize --> Open Projects (or All Projects if not open)

Regards
Dieter
James Shimmon
User offline. Last seen 13 years 31 weeks ago. Offline
Joined: 12 Jan 2007
Posts: 93
Cristina
The only thing I can think of is to open and summarise the copied project then the info should show up in the projects view

Shimmo
Arnold Puy
User offline. Last seen 9 years 14 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Cristina,

Sorry, it’s not so clear can you explain a little bit in detail.

Regards,