I created a copy of a (cost loaded) project in P6. I wonder why in Projects the Total Activities & BAC columns for the copy show 0 (zero).
When I open the copy, its fine; has all the data & info I need. But...guess what...the original project gets...depleted from this info (showing 0 activites & costs).
Can anybody explain me what is happeening or why?
When I open the copy, its fine; has all the data & info I need. But...guess what...the original project gets...depleted from this info (showing 0 activites & costs).
Can anybody explain me what is happeening or why?