Baseline Bar - P6.0

7 replies [Last post]
Xiaobao Lei
User offline. Last seen 15 years 6 weeks ago. Offline
Joined: 20 Mar 2009
Posts: 6
Groups: None
Hi Planners,

There is one headache problem in P6.0.

When there are some actual activities and I rebaseline the project, the rebaseline bars of those actual activities just shows their "Planned Dates", but not "Current Dates", in another word, the rebaseline bar is shorter then current bar even I’ve not done any updates.

This is not good to compare the progress.

In P3.1 there is no this problem.

Can anyone help on this? Appreciate!

Replies

Arnold Puy
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Mr. Xiaobao Lei,

Thank you so much for that. We are happy to help.

Regards,

Arnold

Xiaobao Lei
User offline. Last seen 15 years 6 weeks ago. Offline
Joined: 20 Mar 2009
Posts: 6
Groups: None
Hi Arnold, I should call you Mr. Expert.

Yes,you are right. It is fixed. Appreciate!

Regards,
Arnold Puy
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Lei,

Sorry for the blank post. Because, my internet connection is having the problem!!!

Try to go to Admin --> Admin Preferences, under the Earned Value tab, Earned value calculation: The Default is "Budgeted values with planned dates" try to change to "Budgeted values with current dates" and then close.

Regards.



Arnold Puy
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Arnold Puy
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Xiaobao Lei
User offline. Last seen 15 years 6 weeks ago. Offline
Joined: 20 Mar 2009
Posts: 6
Groups: None
Thanks for comments, Arnold.

Yes, it is baseline bar. The problem is that this baseline bar just links to its "Planned Date", but not the "current date" of its rebaseline date.
Arnold Puy
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Lei,

Make sure that the bar you displayed is the baseline bar.