P3e progress bar against baseline bar
Forum Sponsor
Top Posters
Dimitrios Theocharidis
3 posts
MichaelFuelsC
0 posts
anwar zeb
1 posts
olva seselima
1 posts
Muhammd Muneer
0 posts
sairam
0 posts
MARAT BILYALOV
0 posts
RichTea66
0 posts
Muneer Muhammad
1 posts
Manny Onifade
5 posts
choose the "%complete bar" under the "TimeScale" column from the "Bars" option. Make %Complete Type as Physical from the GeneralTab of Activity Details Window.
bye the way, is this the one you are expecting or something else?.
Thanks for that, but that is what i already have. that gives me a % progress bar against the current (actual & forecast bar. What I am after is the % complete bar against the baseline bar.
eg if the baseline bar finishes in aug and the current is complete the progress bar finishes to the left of the data date.
also if the end date of the baseline bar is past the progress bar can come past that enddate if the current is not complete. I find people like to track progress against a baseline (agreed plan, not against the current which is dynamic and always changing. your planned dates & planned progress figures also come from the baseline.
Regards