Hi Planners,
There is one headache problem in P6.0.
When there are some actual activities and I rebaseline the project, the rebaseline bars of those actual activities just shows their "Planned Dates", but not "Current Dates", in another word, the rebaseline bar is shorter then current bar even Ive not done any updates.
This is not good to compare the progress.
In P3.1 there is no this problem.
Can anyone help on this? Appreciate!