P3 Target bars vs. P6 Baseline Bars

6 replies [Last post]
James Braghini
User offline. Last seen 13 years 27 weeks ago. Offline
Joined: 28 Apr 2008
Posts: 51
Groups: None
I give up. How can I do the same thing in P6 like we did in P3 for comparing Target Bars? I have tried different ways but can never get the Secondary Bar to move seperatly from the Primary Bar in P6.

Any guideness would be appreciated.

James B.

Replies

yasser abouzeid
User offline. Last seen 12 years 5 weeks ago. Offline
Joined: 13 Feb 2011
Posts: 2
Groups: None
Kanishka Sauis
User offline. Last seen 8 years 19 weeks ago. Offline
Joined: 19 Dec 2011
Posts: 2
Groups: None

Thank u Guys much appreciated :)

Ali Farhat
User offline. Last seen 13 years 42 weeks ago. Offline
Joined: 23 Oct 2008
Posts: 120
Groups: None
James,
if your problem is NOT seeing the secondary baseline bar on the gantt chart.
right click on gantt chart, bars..
click on "second baseline", change the timescale to "secondary baseline" (it is not the default option)
make sure each of the three bars (current, first and second baseline) do not coincide, that is having different rows.
Carmen Arape
User offline. Last seen 6 years 36 weeks ago. Offline
Joined: 26 Jun 2004
Posts: 292
James,

In P6 you have Project assign and maintain baselines.

Assign baseline: you assign the baseline that you would like to show.
Maintain baseline: you CREATE the baselines.

Before working with the bars that you want to display, you must assign the baseline.

ONCE that you have selected the baseline bar, paying attention to the content of columns name and timescale you will get the filter.
It is a predefined filter.

HTH

Cheers,
James Braghini
User offline. Last seen 13 years 27 weeks ago. Offline
Joined: 28 Apr 2008
Posts: 51
Groups: None
Oliver:

I did that and still have the same problem. Does the filter used make a difference? Is there something that I am doing wrong when I update the baselines?

James B.
Oliver Melling
User offline. Last seen 4 years 30 weeks ago. Offline
Joined: 24 Apr 2007
Posts: 595
Groups: The GrapeVine
James,

Check Project, Assign baselines and ensure you have the correct baseline assigned as the secondary one.

Also, right click on the gantt, select bars and check that second baseline is ticked and the timescale is secondary baseline.