Display progress on target bar for P5

1 reply [Last post]
Jerry Lan
User offline. Last seen 6 years 23 weeks ago. Offline
Joined: 12 Sep 2006
Posts: 37
Dear all,

In P3, there is the option whereby we can display progress on target bar. I do not want to display progress on the current bar. I think that was very good thing in P3. Is this possible in P5? If yes, how? Thanks in advance!


Regards,
Jerry

Replies

Andrew Pearce
User offline. Last seen 37 weeks 4 days ago. Offline
Joined: 11 Jun 2001
Posts: 174
I put up a similar posting earlier this year.
It is possible to overlay a %complete bar on a baseline bar, the problem is that the % bar is drawn starting on Actual start date, not on baseline start date as in P3.