Oracle Primavera - PM6 Member for 24 years 4 months Member for 24 years 4 months Submitted by Andrew Pearce on Fri, 2007-11-02 05:54 Permalink RE: Display progress on target bar for P5 I put up a similar posting earlier this year. It is possible to overlay a %complete bar on a baseline bar, the problem is that the % bar is drawn starting on Actual start date, not on baseline start date as in P3. Log in or register to post comments
Member for 24 years 4 months Member for 24 years 4 months Submitted by Andrew Pearce on Fri, 2007-11-02 05:54 Permalink RE: Display progress on target bar for P5 I put up a similar posting earlier this year. It is possible to overlay a %complete bar on a baseline bar, the problem is that the % bar is drawn starting on Actual start date, not on baseline start date as in P3.
Member for
24 years 4 monthsRE: Display progress on target bar for P5
I put up a similar posting earlier this year.
It is possible to overlay a %complete bar on a baseline bar, the problem is that the % bar is drawn starting on Actual start date, not on baseline start date as in P3.