viewing relationships with baseline bars displayed

When you are displaying both current project and a baseline bar and select "show relationships" from barchart options, the relationship lines are shown linking the baseline bars and not the current project bars.

 

Anyone know of a way to fix this?

 

Cheers,

 

G

G
Gary Whitehead 👤 Member for 17 years 2 months

Thanks, Ferdinand.

 

-I had just worked it out myself, but your swift reply means none of my colleague's believe me!

 

Cheers,

G

F
Ferdinand U. 👤 Member for 18 years 10 months

from bars

move the display name of remaining bar on top of the baseline bar