How can I display the progress agaist the baseline bar?

3 replies [Last post]
Ayman Eleish
User offline. Last seen 12 years 1 week ago. Offline
Joined: 28 Dec 2010
Posts: 48
Groups: None

Hi all,

How can I display the progress agaist the baseline bar?and summarize it?

thanks.

Replies

Ayman Eleish
User offline. Last seen 12 years 1 week ago. Offline
Joined: 28 Dec 2010
Posts: 48
Groups: None

Hi Sanad,

Is it possible to update progress in target and reflect it as progress bar for base line,as we used to do it in p3 to compare the current project progress versus the planned progress (blue bar)whether by cost or by time.

sanad ahmed
User offline. Last seen 9 years 24 weeks ago. Offline
Joined: 6 Dec 2010
Posts: 7
Groups: None

Show schedule% complete againest Performance % complete

Sanad A Ragaee, PMP

sanad ahmed
User offline. Last seen 9 years 24 weeks ago. Offline
Joined: 6 Dec 2010
Posts: 7
Groups: None

Also you could Show earned value vs planned value cost

Sanad A Ragaee, PMP