How to create a WBS UDF that can be displayed at Activity level, same as WBS Category can be displayed.

No replies
Rodney Jones
User offline. Last seen 1 year 16 weeks ago. Offline
Joined: 18 Jun 2012
Posts: 65
Groups: None

Hello Everyone,

 

I am wondering how to create a WBS UDF that can be displayed at Activity level, same as WBS Category can be displayed and grouped at Activity Layouts as a column.

Or a WBS code that can be displayed and grouped by at Activity level.

 

Thanks,

 

Rod

Rodney Jones
User offline. Last seen 1 year 16 weeks ago. Offline
Joined: 18 Jun 2012
Posts: 65
Groups: None

Closed.

 

Rodel, Yes, I ended up adding an Activity code. Thanks, Rod

Rodel Marasigan
User offline. Last seen 14 weeks 7 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Rodney,

WBS UDF is only available to assigned on WBS table, if you wanted to Activity Level you can define WBS at Activity UDF. There is no WBS Code or you mean Project Code? Again, Activity Code can be define a WBS definition with hierarchy on single activity code type at activity level. You can create a new WBS definition with hierarchy as up to 20 levels or depending on maximum tree level setting you assigned on Admin preferences.