how can i hide the Bar of WBS summary activity

5 replies [Last post]
Jason LI
User offline. Last seen 5 years 14 weeks ago. Offline
Joined: 1 Jan 2008
Posts: 37

dears,

is it possible to hide the WBS summary activity bar, but it still need to show the WBS summary activity, please advise me.

tank for your help

 

Jason

Replies

Gary Whitehead
User offline. Last seen 6 years 18 weeks ago. Offline

OK then, so you will have to set up a new filter for the critical bar which excludes wbs summaries

Jason LI
User offline. Last seen 5 years 14 weeks ago. Offline
Joined: 1 Jan 2008
Posts: 37

Gary, it's just like your said, this WBS summary activity was on critical path, so if i un-stick the critical remaining bar, the bar will no longer sowing, but all the other critical bars are gone.

 

regards,

Jason

Gary Whitehead
User offline. Last seen 6 years 18 weeks ago. Offline

Not that I am aware of.

 

Only thing I can think is that you have another bar with the same look as the summary bar that you also need to untick -if that's not it, no idea.

Jason LI
User offline. Last seen 5 years 14 weeks ago. Offline
Joined: 1 Jan 2008
Posts: 37

tanks Gary, i have un-tick the Display box, but the bar is still showing. is there any other reason, or other option to hide it.

regards

 

Jason

Gary Whitehead
User offline. Last seen 6 years 18 weeks ago. Offline

right-click anywhere in the gant-cvhart section

select "bars"

scroll down to the "summary" bar

un-tick the "display" box.

click "OK"