Mix summary and detail activities on a graphical report without overlapping jumbled letters next to the summary bar and keep tex

2 replies [Last post]
John Reeves
User offline. Last seen 16 weeks 5 days ago. Offline
Joined: 10 May 2013
Posts: 344
Groups: None

Mix summary and detail bar description names - without a jumbled typo line next to the summary bars.  I guess I could create a custom column and have it blank for WBS items that I will roll-up but I assume there should be a way without the extra step that someone have figured out...

Replies

John Reeves
User offline. Last seen 16 weeks 5 days ago. Offline
Joined: 10 May 2013
Posts: 344
Groups: None

I meant in P6 Primavera Ver 8.x

Mike Testro
User offline. Last seen 39 weeks 3 days ago. Offline
Joined: 14 Dec 2005
Posts: 4420

Hi John

Work on a spreadsheet with the text in different columns and you can concatenate the cells into one text string.

such as:

B3&C3&D3

If you need a text diveder such a a space or - then put this into cell B2 and the concatenation would run:

B3&$B$2&C3&$B$2&D3

This formula can then be coppied down the spreadsheet.

I use concatenation to create text strings for delay analysis reports.

Best regards

Mike Testro