Good afternoon all,
Here is my deliema; we have a baselined, resource loaded schedule that we and the client are happy with. However, within my Gant Chart view I would like to show progress within (small thin blue bar) the baseline bar, currently I am able to do this as long as the baseline bar is inline with the Datadate line,, HOWEVER,, what if my baseline bar is sitting in November and (today being the 23rd July) for some reason we have completed that task this week?, obviously the baseline bar stays in November but the progress bar sits on or to the left of the data date line,, what I would like to happen is this,,, the progress bar moves out to the basline bar where it sits within it (still in November represnting the planned dates), the actual starts and finish dates STILL remain as July BUT the data date (or progrees – I think it is called) line moves directly to the right to indicate the ‘progress’ then directly back in to the current date.
As always, any help that anyone could be would be hugely appreciated.
Many thanks
Jon
Replies