P6 Moving Activity

9 replies [Last post]
Riyadh Yahia
User offline. Last seen 12 years 2 weeks ago. Offline
Joined: 24 Jul 2008
Posts: 62
Hi,

At the time I make scheduling (F9) for P6 project, I notice that the activity date is moving to new date also some activities took the data date itself !!!!!! that hapen also after assigning a baseline.

Any could help ???

Replies

Alex Wong
User offline. Last seen 11 years 5 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
That why I find very hard to explain the MSP project manager to have activity not started and planned in the past....
Riyadh Yahia
User offline. Last seen 12 years 2 weeks ago. Offline
Joined: 24 Jul 2008
Posts: 62
Thanks to ENGR, winter & Engr,Puy

for their full explanation, Now I got the Point as they

explained in detail.

best regards

riad

Ian Adan
User offline. Last seen 14 years 23 weeks ago. Offline
Joined: 20 Oct 2004
Posts: 6
Excellent Mr Winter. You just made my day.
Ronald Winter
User offline. Last seen 3 years 7 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None
Let me add to what Arnold just said…

The start of any unstarted activity with no outstanding predecessor commitments is supposed to move when the data date moves. If it does not then you are talking about MS Project. Unless you have a time machine and are planning to use it to move your work crews back in time, uncompleted work cannot exist in the past. Good luck!
Arnold Puy
User offline. Last seen 9 years 12 weeks ago. Offline
Joined: 25 Apr 2007
Posts: 1147
Hi Riad,

Generally, the Start Date of each Activity will keep on moving as the Data Date move especially when this activity is not yet started and the predecessor of it will keep pushing when there is no progress recorded and also due to driving relationship.

To avoid moving the Start Date, all you have to do is to adjust the LAG or change the Relationship Type. But in this case, you have to inform the Client and you should specify and justify all lags and relationship type.


Regards,

Arnold
Riyadh Yahia
User offline. Last seen 12 years 2 weeks ago. Offline
Joined: 24 Jul 2008
Posts: 62
Dear Wong,

that is the point I can not Put Actual start for

Activities didnot Start YET.

Any Other Sugestion........
Alex Wong
User offline. Last seen 11 years 5 weeks ago. Offline
Joined: 12 Feb 2003
Posts: 874
Groups: TILOS
Well

Have you try to put a actual start date to your activity.

that will stop the Early Start date moving as the data date move :-)

you need to make sure you updated your schedule correctly

Alex
Riyadh Yahia
User offline. Last seen 12 years 2 weeks ago. Offline
Joined: 24 Jul 2008
Posts: 62
Hi Bhedase,

I did as you said, but did not work.....still moving.....

Any other solution please !
A D
User offline. Last seen 3 years 24 weeks ago. Offline
Joined: 20 May 2007
Posts: 1027
Go to tools--> Resources --> go to details tab and check AUTO COMPUTE ACTUALS.

Switch OFF anto compute actuals.

This shud solve ur problem