Budgeted resorses moves with data dates

1 reply [Last post]
Reza Hasheminia
User offline. Last seen 16 years 14 weeks ago. Offline
Joined: 10 Dec 2007
Posts: 7
Dear friends,
I’ve faced a serious problem during updating my project schedule, i’ve assigned nonlabour resoreces to activities and set the schedule as initial plan, after update i found the budgeted resorces moved behind the new data date, so that it’s not posible to compare budgeted and actual resources.
please advise.
Many thanks.

Replies

Gordon Blair
User offline. Last seen 6 years 6 weeks ago. Offline
Joined: 29 Jul 2005
Posts: 166
Groups: None
Have you updated the Resource % complete in the Resources Tab?