P6, Modify data date and date interval lines types

2 replies [Last post]
Abeer Mahmoud
User offline. Last seen 7 years 41 weeks ago. Offline
Joined: 8 Jul 2008
Posts: 87
Hi All,

Can you please advise me how can I modify above mentioned lines types in P6?


Regards,
Abeer

Replies

Abeer Mahmoud
User offline. Last seen 7 years 41 weeks ago. Offline
Joined: 8 Jul 2008
Posts: 87

Osama
I wonder how I forget this command. Thanks for your reminder.

Regards,
Abeer
osama Eltantawy
User offline. Last seen 13 years 52 weeks ago. Offline
Joined: 25 Jan 2009
Posts: 12
Groups: None
High Abeer,
Go to View menu
Bar Chart options
you can edit now.
Thank you