Good morning all,
As always, any help that anyone could be would be very much appreciated.
Here is the issue I seem to be having,,, I have a Resource Loaded plan that I am running a Report (Activity Resource and Role Assignment in Subject Area), everything works as you would expect, I like to create the CSV. File so I can manipulate my data,,, however,, when I set the date interval to WEEK within Timescale my start and finish dates are in the (week beginning) week too late,, for example, I have four activities that finish on the 6th August but the report (when run on WEEK date interval) leaves me hours remaining in the week beginning the 10th August,, conversely, if I run the very same report by DAY all four finish on the 6th August
Has anyone else encountered this? If so, is there a fix?
Many thanks
Jon