Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

How to Change Cutt off dates (weekly base)

3 replies [Last post]
paulvllnv
User offline. Last seen 11 years 3 weeks ago. Offline
Joined: 16 Sep 2010
Posts: 2
Groups: None

dear all,

hoa to change the cut off date in P6? in the schedule the cut off date falls every sunday, but i want it to be change every friday. thanks

Replies

Zoltan Palffy
User offline. Last seen 19 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3088
Groups: None

admin 

admin preferences

General tab

Starting Dau of Week Chanhe this to Saturday

this will end the week on Friday

mohamed azarudeen
User offline. Last seen 4 years 40 weeks ago. Offline
Joined: 10 Jun 2019
Posts: 2
Groups: None

Select Enterprise-> Calendar from Primavera menu. Then select which one you need (Global, Resource or Project) to create. Click Add or modify existing and define it from there.

niles luo
User offline. Last seen 12 years 44 weeks ago. Offline
Joined: 25 Nov 2005
Posts: 46
Groups: None

hi,

    We can set it at Admin preferences->General->starting day of week.

Best Regards.