Hi Guys,
Hopefully there is a genius out there that is an expert with filters and or global changes, I am after a solution and can’t work out if it is possible to do in P6.
Based on a filter (using codes to select a group of activities) I want to write a value into two date UDF Fields can I:
1. Run a global change to give the earliest and latest date in the group and write the result to all tasks in the group? or
2. Is there a mindate maxdate option in Global change or filter? Or
3. If these tasks were grouped in the activity view can a global change be written to fill down the dates that the summary level is displaying, which are essentially the min and max dates of the groups.
· I could do this pretty easily in excel but I have over a 100 projects and doing the import one at a time is not feasible.
· I could create LOE’s but as my variables are constantly changing and due to the volume also not an option.
· Summary bars are not an option eithers as I am writing the UDF’s to get all the bars I want on one line, An option for me might be to do it using Legare but I would prefer to see if I can get it done in P6 first.
Cheers Rob
Replies