When to Move the Data Date

5 replies [Last post]
Jason LI
User offline. Last seen 3 years 37 weeks ago. Offline
Joined: 1 Jan 2008
Posts: 37

Dears,

During the schedule update, what's the standard process,

a: Input the actual, etc. information then move he data date, then calculate.

b: move the data date, then Input the actual, etc. information , then calculate

 

Thanks for your reply.

Jason

 

Replies

Zoltan Palffy
User offline. Last seen 19 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3088
Groups: None

you got it right 

determine what date that you wil be recording progress thru. Lets say you wanted to record progress for the month of November.

first copy the existing project

next input All actuals by clikcing on the status tab then if an activity actually started in November check the box next the word started and then put the actual stat date in the box next to the word started if the activitiy also finished in Novemebr then do the same procedure for the finished box.

If an activity started in November but is not yet finished check the box next to the word started and then put the actual start date in the drop down box next to the word started. Now click in the remaing duration box and put in the remining duraiton that it wil take to complete the remainder of the work. 

change data date by pressing the f9 function key and change the date to December 1

click on calculate 

repeate this for every update period

Satheesh Kumar Ra...
User offline. Last seen 9 years 14 weeks ago. Offline
Joined: 4 Dec 2014
Posts: 2

How to Do this ? ANy Example Please!

Raymund de Laza
User offline. Last seen 26 weeks 3 days ago. Offline
Joined: 22 Nov 2009
Posts: 762

Likewise here, Update Activities then Move the DD.

Zoltan Palffy
User offline. Last seen 19 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3088
Groups: None

you got it right 

input All actuals 

change data date

calculate 

repeate this for every update period

Michelle Morch
User offline. Last seen 9 years 20 weeks ago. Offline
Joined: 14 Apr 2011
Posts: 8

I always input the actuals before moving the data date.