Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

WBS Summary Activites Moving with Data Date

1 reply [Last post]
Nathan Siva
User offline. Last seen 54 min 20 sec ago. Offline
Joined: 28 Apr 2014
Posts: 26
Groups: None

Hi Experts,

 

I'm Facing an issue, In my schedule, even though some of the WBS summary activities are already started, they are moving with the data date of the schedule.

Every time when I'm changing the data date, WBS summary activites moving forward with the data dates and then I have to revise back to previous dates of WBS Summary.

Kindly advise.

Replies

Alexandre Faulx-B...
User offline. Last seen 1 hour 5 min ago. Offline
Joined: 20 Jan 2003
Posts: 1315

Hi Nathan,

Please check that the bar for the wbs summary activities is not displaying the remaining duration only, but also the actual duration.

Alexandre