Hi Experts,
I'm Facing an issue, In my schedule, even though some of the WBS summary activities are already started, they are moving with the data date of the schedule.
Every time when I'm changing the data date, WBS summary activites moving forward with the data dates and then I have to revise back to previous dates of WBS Summary.
Kindly advise.