Ive faced a serious problem during updating my project schedule, ive assigned nonlabour resoreces to activities and set the schedule as initial plan, after update i found the budgeted resorces moved behind the new data date, so that its not posible to compare budgeted and actual resources.
please advise.
Many thanks.