Impact of Global calendar vs Activity based calendar

3 replies [Last post]
Farhan Aftab
User offline. Last seen 5 years 29 weeks ago. Offline
Joined: 8 Aug 2018
Posts: 3
Groups: None

Hi Guys,

If a programme has a default Global calendar with two days a week off ( sat/sunday), and it is ticked as default in calendars. But, the individual activities have three different calendars, 6 days a week, 7 days a week and the default one, stated above.

Which one takes precdence in scheduling? What is the difference between default calendar and then choosing separate activity based calendars?

Thanks

Replies

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

glad I could help 

Farhan Aftab
User offline. Last seen 5 years 29 weeks ago. Offline
Joined: 8 Aug 2018
Posts: 3
Groups: None

Thanks Zoltan ; Noted.

Zoltan Palffy
User offline. Last seen 3 weeks 4 days ago. Offline
Joined: 13 Jul 2009
Posts: 3089
Groups: None

NONE take precedence its whatever your calendar  that the activity is assigned to. BY design when adding a new activity will automatically be assigned to the calendar listed in the defaults tab which is in the projects directory