Hi Guys,
If a programme has a default Global calendar with two days a week off ( sat/sunday), and it is ticked as default in calendars. But, the individual activities have three different calendars, 6 days a week, 7 days a week and the default one, stated above.
Which one takes precdence in scheduling? What is the difference between default calendar and then choosing separate activity based calendars?
Thanks