Has your question already been answered?

Get a quicker response; before you post, why not search to see if it has already been answered

Duration Difference - At Completion Duration based on Default Calendar

2 replies [Last post]
Jithin Kambhikanam
User offline. Last seen 1 week 2 days ago. Offline

Hello Everyone,

The is a Difference in Duration in the WBS. The Project Duration is shown as 174 Days and Milestone Duration is 243 Days (which is the calendar days).

5324
wbs_date.jpg

 

I have 3 Types of Calendar in the Project a). 5 Days Work Week, b). 6 Day Work Week and c). 7 Day Work Week.

The Default Calendar of the Project is 7 Days Work Week.

Could you please guide me on how to show in the Project Duration as 243 Days (Calendar Days).

 

Regards

Jithin

Replies

Zoltan Palffy
User offline. Last seen 1 day 18 hours ago. Offline
Joined: 13 Jul 2009
Posts: 1940

just make sure that you set a defaul calendar for the PROJECT

Jithin Kambhikanam
User offline. Last seen 1 week 2 days ago. Offline

HI Everyone,

 

Got the Answer after doing some research,

 

I went to Enterprise - Calendars - Global Section - Then I moved Default Calandar Tick from the Calendar which had a 5 Day Work week to 7 Day Work Week.

Now the Total Duration is same as the the Below WBS Duration.

 

Regards

Jithin