Global and Project calendars

1 reply [Last post]
Nkoketseng Konopi
User offline. Last seen 15 weeks 2 days ago. Offline
Joined: 18 Feb 2013
Posts: 6

Hi All

How do you tell whether an assigned calendar on P6 is the global or the project calendar if you have the same calendar name under the global and the project calendar libraries?

Replies

Nkoketseng Konopi
User offline. Last seen 15 weeks 2 days ago. Offline
Joined: 18 Feb 2013
Posts: 6

Thanks Rodel. That sounds liek a simple enough solution. I was hoping or thinking that there was an easy way of confirming this without any such manipulation, but I note you suggestion. It would have been good if P6 used a different icon for instance for the Global calendars and another for the project calendars tp provie an easy way of knowing where the calendar is hosted.

Rodel Marasigan
User offline. Last seen 4 days 6 hours ago. Offline
Joined: 25 Oct 2006
Posts: 1699

Simply rename one of the calendars (either the global or project calendar), and you will see which calendar is assigned to your project. If the assigned calendar is the one you renamed, it will automatically update to the new name.