Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

7-days calendar vs. resource loaded schedule

1 reply [Last post]
Bo Johnsen
User offline. Last seen 8 years 8 weeks ago. Offline
Joined: 28 Feb 2006
Posts: 119
Many Owners/Clients want to have a WBS-programme submitted in calendar days, i.e. 7-days calendar. At the same time they also want a resource loaded schedule, not just names of resources, but also number of units (workers).

Doesn’t that defeat the object if the Contractor only works 5 or 6 days a week? By adding in resources the manhours will be higher than what is actually worked on site and the schedule can’t really be used for tracking of manhours - unless the Contractor have a seperate, identical schedule in working days (i.e. 5 or 6 days week in this case).

How is it possible to satisfy the Owner’s requirement and at the same time utilizing this schedule for manhours tracking purposes being the Contractor?

rgds,

Bo

Replies

James Griffiths
User offline. Last seen 15 years 15 weeks ago. Offline
Joined: 19 May 2006
Posts: 435
Groups: None
Hi Bo,

I assume that you do not normally provide a resource-loaded programme? If this is the case, then the client’s request for a resource-loaded programme will give him the abiity to "play" with the programme in order to determine the various effects of adding or removing resources (using the same total value of hours), changing the number of working-days-per-week etc. etc. This can only be done if you have the resource loading (hours-per-activity). A simple example: If you have a 30-day activity, employing 10 people at 100% level of effort, then they can see that, mathematically, the duration of that activity could be 15 days if they employed 20 people - but this would affect the project’s cash-flow profile.

If the contract has already been signed, then it is rather unfair of the client to ask for a resource-loaded programme. If he has access to this data, then he can start interfering even more than usual, by offering his very helpful "advice".

HTH.

James.