Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

One (1) day Calendar Issue

1 reply [Last post]
Muhammad AQEEL
User offline. Last seen 13 years 28 weeks ago. Offline
Joined: 9 Oct 2010
Posts: 12
Groups: None

URGENT!!!

Dear All,

I 'm facing a problem with clander like;

One i give duration One day e.g: activity start on 12/10/2010 and will be finish on 12/10/2010 than this will be consider one right duration  But with me on the schedule date is comning 13/10/2010 instead on 12/10/2010 and showing the org. Duration is 1 (one). Can some one fix this problem. this will be much appriciated.

Regards,

maqeel

(maqeel2008@hotmail.com)+966599981584

Replies

Ronald Winter
User offline. Last seen 3 years 6 weeks ago. Offline
Joined: 4 Jan 2003
Posts: 928
Groups: None

P6 is not a day-oriented CPM software.  Activities are scheduled down to the minute.  To understand your issue, you will need to display hours and minutes as well as days.  Once you do, I am sure that the answer to your problem will be evident.  Good luck!