Don't you have to "add new calendar" every time, or a change in the Calendar will change old schedules?

No replies
John Reeves
User offline. Last seen 1 week 1 day ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

Don't you have to "add new calendar" every time, or a change in the Calendar will change old schedules? - if not, why not?

Santosh Bhat
User offline. Last seen 1 year 3 weeks ago. Offline
Joined: 15 Apr 2005
Posts: 381

If you overwrite an existing calendar in a P6 database, yes all projects that use that calendar may be affected. I say "may" as this will only happen once those projects are opened and then re-calculated.