Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

2 weeks of work, so you give them 4 weeks because you don't want to deal with possible 2nd extension- cost?

1 reply [Last post]
John Reeves
User offline. Last seen 1 day 10 hours ago. Offline
Joined: 10 May 2013
Posts: 343
Groups: None

2 weeks of work, so you give them 4 weeks because you don't want to deal with possible 2nd extension- cost?  - Can you ask or expect only having to pay for 2 weeks of overhead for 4 weeks of work - for the above reason.  Would you be concerned that they agree and then address different legally?

Replies

Larry Rino
User offline. Last seen 50 weeks 2 days ago. Offline
Joined: 25 Oct 2007
Posts: 64

John, without knowing your contract pricing conditions and other circumstances, it's typical that daywork rates is used for additional work and that rates includes overhead, if that so, then 2-weeks extension will be fine...