Scope Change- additional project to existing project

3 replies [Last post]
Sharaf Labod
User offline. Last seen 7 years 26 weeks ago. Offline

Dear all,

There is additional two new building project that was added to 6 existing building projects. the 6 building are almost complete while the two new ones are still in the structural stage.

The two new building contract were signed as an annexture to the main contract beacuse the value exceeds 20% of the original scope amount.

The existing  6 buildings project has a single baseline substantial completion of each building as a milestone with a cumulative 95% completion while the 2 new added building are are not included in the project baseline yet because the contract amount has just been finalised and signed.

Question

1. Do we re-baseline the 6 building project and add the two or maintain a seperate baseline program for the two new buildings considering the fact that its a single contract.

Note: the contractor has already started work on the two new sites with a tentative program being maintained seperately to monitor the progress.

The buidings are all typical .

 

Your professional opinions required please.

 

Replies

Mary Louis
User offline. Last seen 7 years 25 weeks ago. Offline
Joined: 28 Oct 2016
Posts: 3
Groups: None

duplicate comment. deleted.

Mary Louis
User offline. Last seen 7 years 25 weeks ago. Offline
Joined: 28 Oct 2016
Posts: 3
Groups: None

Came across this Scope Management link   You might find some useful information there. 

Best regards,

Mary Louis 

Project manager, PMP certification

Mike Testro
User offline. Last seen 5 weeks 5 days ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Sharaf

Since the two new buildings are being treated as a variation to the original 6 building contract then all 8 buildings should be put into the same baseline programme and a new completion date negotiated.

Never have two contracts on one site with one contractor - massive problems will flow from that scenario.

Best regards

Mike Testro