Actual ManHr

1 reply [Last post]
TUNJI ADEWALE
User offline. Last seen 4 years 20 weeks ago. Offline
Joined: 18 Jul 2014
Posts: 13

Dear All,

 

What are the best practice to report and monitor actual manpower/manhr spent on each activity?

Replies

Shah. HB
User offline. Last seen 19 weeks 1 day ago. Offline
Joined: 25 Nov 2008
Posts: 773

Hi Yakubu,

Timesheets (Manual Entry) or biometric clocks show the actual manpower and hours spent in the project.

Form the hours spent information; you can segregate normal work hours and overtime, which can be tied in with the rates for processing pay rolls.

 

Cheers

Shahul Badhusha