Guild of Project Controls: Compendium | Roles | Assessment | Certifications | Membership

Tips on using this forum..

(1) Explain your problem, don't simply post "This isn't working". What were you doing when you faced the problem? What have you tried to resolve - did you look for a solution using "Search" ? Has it happened just once or several times?

(2) It's also good to get feedback when a solution is found, return to the original post to explain how it was resolved so that more people can also use the results.

Number of days problem

4 replies [Last post]
siva ganesh
User offline. Last seen 9 years 39 weeks ago. Offline
Joined: 1 Dec 2011
Posts: 24
Groups: None

Hello friends,

 I have a small problem regarding the number of duration for activities. Example: Activity 1 has the original duration as 5 days. but the dates are as follows,Start -- 20 feb 2013Finish -- 25 feb 2013 But if we count the number of days, it actually 6 days..I need finish date should be 24 feb 2013. 1st day -- 20 feb 20132nd day -- 21 feb 20133rd day -- 22 feb 20134th day -- 23 feb 20135th day -- 24 feb 2013 is it any setting problem??? please help me to sort out. Thanks,Sivaganesh

Replies

siva ganesh
User offline. Last seen 9 years 39 weeks ago. Offline
Joined: 1 Dec 2011
Posts: 24
Groups: None

thanks everyone....

Gary,

it is correct but confusing.

Start at 8am on 20th of February and Finish at 17pm on 24th of February is also correct but not confusing.

Finishing project on Friday evening or on Monday morning is the same but those who want to use the product on Saturday may be disappointed.

Raymund de Laza
User offline. Last seen 30 weeks 6 days ago. Offline
Joined: 23 Nov 2009
Posts: 762

Sivaganesh,

Check this in your Schedule.

 

20 Feb = 8:00am - 5:00pm
21 Feb = 8:00am - 5:00pm
22 Feb = 8:00am - 5:00pm
23 Feb = 8:00am - 5:00pm
24 Feb = 8:00am - 5:00pm

 

Day 1 
20 Feb = 12:00pm -                
21 Feb =               - 11:59am

Day 2
21 Feb = 12:00pm -
22 Feb =               - 11:59am
 

Day 3
22 Feb = 12:00pm -
23 Feb =               - 11:59am

Day 4
23 Feb = 12:00pm -
24 Feb =               - 11:59am

Day 5
24 Feb = 12:00pm -
25 Feb =               - 11:59am
 

 

 

 

Gary Whitehead
User offline. Last seen 4 years 45 weeks ago. Offline

Sivaganesh,

 

If you start activity 1 at 8am on 20th Feb, and it is 5 days duration, it will finish at 8am on 25th Feb.

 

This is correct.