Hello friends,
I have a small problem regarding the number of duration for activities. Example: Activity 1 has the original duration as 5 days. but the dates are as follows,Start -- 20 feb 2013Finish -- 25 feb 2013 But if we count the number of days, it actually 6 days..I need finish date should be 24 feb 2013. 1st day -- 20 feb 20132nd day -- 21 feb 20133rd day -- 22 feb 20134th day -- 23 feb 20135th day -- 24 feb 2013 is it any setting problem??? please help me to sort out. Thanks,Sivaganesh