Can you limit number of activities on a day?

2 replies [Last post]
Philip Attersal
User offline. Last seen 31 weeks 3 days ago. Offline
Joined: 9 Feb 2016
Posts: 4
Groups: None

Hi All

Firstly. I am a lvl 3 planner. And a new one at that. More used to reviewing contractors programmes, than building ones...

So. Question 

I am building a programme, where upon only we have a deliverable to be discussed at a weekley meeting

Problem is. We only have two meetings a week. And can only discuss so many deliverables per meeting

If I create a new calender for the meetings, can I create a 'rule' of some king. Ie. If more than 3 deliverables are forecast to the meeting, it will jump to the next one?

 

Regards

Philip 

Replies

Philip Attersal
User offline. Last seen 31 weeks 3 days ago. Offline
Joined: 9 Feb 2016
Posts: 4
Groups: None

Thank you. Just need to work out how to do that. I've never used resources in P6 

Bit of trial and error :-) 

Mike Testro
User offline. Last seen 1 day 19 hours ago. Offline
Joined: 14 Dec 2005
Posts: 4418

Hi Philip

In most programmes you can put in a resource levelling system on your deliverable resource - allowing only 2 per week.

Best regards

Mike Testro