Hi All
Firstly. I am a lvl 3 planner. And a new one at that. More used to reviewing contractors programmes, than building ones...
So. Question
I am building a programme, where upon only we have a deliverable to be discussed at a weekley meeting
Problem is. We only have two meetings a week. And can only discuss so many deliverables per meeting
If I create a new calender for the meetings, can I create a 'rule' of some king. Ie. If more than 3 deliverables are forecast to the meeting, it will jump to the next one?
Regards
Philip